吊鉤式拋丸機安裝試機注意事項
- 2021-06-03-
這吊鉤式拋丸機一般外觀較大,安裝過程相對比小型設備複雜。正確的安裝和試機是保證後期設備正常運行的關鍵。在初次操作不熟練的情況下,請用戶嚴格按照相關人員的指示或參照使用說明進行操作。未經授權的操作很容易造成不可逆轉的損壞吊鉤式拋丸機. 這shot blasting machine manufacturer has sorted out the precautions for installation and test machine to share with you. I hope it will be helpful to users who use the device for the first time.
1. Installation. 這吊鉤式拋丸機 is installed and debugged in the production plant and disassembled into several parts before being transported to the user site for installation. Although there is no pit, the foundation must be firm, the anchor bolt holes must be standardized, and the chamber body must be adjusted. After the second irrigation, the anchor bolt nuts can be tightened after solidification. After the chamber body is fixed, the various parts can be installed. 這precautions for the installation and debugging of the relevant components are introduced below.
1、拋丸裝置:
這shot blasting device has been installed on the chamber body before leaving the factory. Please pay attention to the problems to be debugged before use. Check whether the fixed positions of the blade, the pill wheel, the directional sleeve, and the guard plate are accurate and firm, and check whether the direction of rotation is correct after power on. Then adjust the position of the directional sleeve opening. Theoretically, the angle between the front edge of the directional opening and the front edge of the blade throwing position is about 900. After fixing the position of the directional sleeve, the position of the projectile belt can be detected by hanging Place a steel plate or wooden board on the position of the workpiece facing the exit of the shot blasting machine, start the shot blasting machine, put a small amount (2-5kg) of projectiles into the blasting tube, and then stop, check whether the hit position on the steel plate is suitable for the needs, such as Close the window of the bias-adjustable directional sleeve downwards, and vice versa, until it fits, and note the position of the directional sleeve opening as a basis for future replacement of the directional sleeve.
2、提昇機和螺旋輸送機:
首先進行空載試驗,檢查提升斗和螺旋葉片的運行方向是否正確,然後將提昇機的皮帶張緊到適度的張緊度以避免跑偏,然後進行負載試驗檢查運行和輸送能力,是否有任何異常噪音和振動,檢查並清除障礙物。
3、丸砂分離機:
先檢查閘板運動是否靈活,再檢查隔板位置是否正確,然後在葫蘆裝車調試時,鋼丸是否不斷流入,檢查鋼丸是否有流出和落下當溜槽卸料時